The design started in december 2013 and we secured the planning consent 4 months, including all needed preliminary consultations.The job started on site 2 months after the granting of the consent and is due to be completed early December 2014. Total delivery time, including design, consultations, planning, tender and construction- 12 months. The design is sleek, modern and, although the loft extension is taller and more spacious than any other extensions in the area, it was conceived not to be intrusive.